BOLIVAR DAFT & PGT’S OPTIONS ASSESSMENT

CLIENT: Aurecon

DATES: 2018    

LOCATION: Bolivar, SA

The scope of work involves upgrading of three dissolved air flotation tanks (DAFT) and the supply, installation and commissioning of two new primary gravity thickeners (PGT). Project also includes the decommissioning/isolation of DAFTs while upgrades are being commenced.

OUR INVOLVEMENT

 

Capisce Qs provided cost estimations on the design and construct of the dissolved air flotation tanks and the primary gravity thickeners.

 

VALUE ADDED


With our ability to think logically, practically and the ability to visualise processes within the project we assisted in the development of the full scope required for the project.