WHYALLA STEELWORKS PROJECT
CLIENT: WSP
CAPEX: AUD 50M
DATES: 2018
LOCATION: Whyalla, SA
WHYALLA STEELWORKS PROJECT
CLIENT: WSP
CAPEX: AUD 50M
DATES: 2018
LOCATION: Whyalla, SA
WHYALLA STEELWORKS PROJECT
CLIENT: WSP
CAPEX: AUD 50M
DATES: 2018
LOCATION: Whyalla, SA
WHYALLA STEELWORKS PROJECT
CLIENT: WSP
CAPEX: AUD 50M
DATES: 2018
LOCATION: Whyalla, SA
The Whyalla Steelworks, under new ownership, is exploring ways to increase the capacity, by up to 50%, and improve cost efficiency through improvement of the current plants equipment and harnessing lost energy of the current plant.
OUR INVOLVEMENT
Capisce Qs was engaged through the owner’s engineering management team to develop cost estimating guidelines and assisting in preparing and reviewing independent cost estimates of the current projects. Further activities have included providing probabilistic risk estimate ranging facilitation.
VALUE ADDED
Capisce Qs continues to provide probabilistic risk estimating and review services across a number of priority projects. This service has enabled informed decision making on project feasibility in a timely manner allowing focus on developing and improving value initiatives on the projects with a higher chance of success.
The Whyalla Steelworks, under new ownership, is exploring ways to increase the capacity, by up to 50%, and improve cost efficiency through improvement of the current plants equipment and harnessing lost energy of the current plant.
OUR INVOLVEMENT
Capisce Qs was engaged through the owner’s engineering management team to develop cost estimating guidelines and assisting in preparing and reviewing independent cost estimates of the current projects. Further activities have included providing probabilistic risk estimate ranging facilitation.
VALUE ADDED
Capisce Qs continues to provide probabilistic risk estimating and review services across a number of priority projects. This service has enabled informed decision making on project feasibility in a timely manner allowing focus on developing and improving value initiatives on the projects with a higher chance of success.
The Whyalla Steelworks, under new ownership, is exploring ways to increase the capacity, by up to 50%, and improve cost efficiency through improvement of the current plants equipment and harnessing lost energy of the current plant.
OUR INVOLVEMENT
Capisce Qs was engaged through the owner’s engineering management team to develop cost estimating guidelines and assisting in preparing and reviewing independent cost estimates of the current projects. Further activities have included providing probabilistic risk estimate ranging facilitation.
VALUE ADDED
Capisce Qs continues to provide probabilistic risk estimating and review services across a number of priority projects. This service has enabled informed decision making on project feasibility in a timely manner allowing focus on developing and improving value initiatives on the projects with a higher chance of success.
The Whyalla Steelworks, under new ownership, is exploring ways to increase the capacity, by up to 50%, and improve cost efficiency through improvement of the current plants equipment and harnessing lost energy of the current plant.
OUR INVOLVEMENT
Capisce Qs was engaged through the owner’s engineering management team to develop cost estimating guidelines and assisting in preparing and reviewing independent cost estimates of the current projects. Further activities have included providing probabilistic risk estimate ranging facilitation.
VALUE ADDED
Capisce Qs continues to provide probabilistic risk estimating and review services across a number of priority projects. This service has enabled informed decision making on project feasibility in a timely manner allowing focus on developing and improving value initiatives on the projects with a higher chance of success.

VARIOUS UNDERGROUND ASSETS
CLIENT: BIS Oxford
DATES: 2018
LOCATION: Adelaide, SA
This project involves implementing a cost exercise for the per km laying of pipe/cable for the construction (supply and installation) of the following five nominated assets: Water Pipes, Sewer Pipes, Gas Pipes, Electricity Cables & Telecommunication Cables
OUR INVOLVEMENT
Capisce Qs provided a detailed cost plan breakdown of the laying of pipe/cable of the five nominated assets per km.
VALUE ADDED
The high level established unit rates were formed using industry knowledge held by our organisation and extensive experience within our team to give a practical average rate that can be utilised to derive indicative total asset costs nationally.